SQL Server administration and T-SQL development, Web Programming with ASP.NET, HTML5 and Javascript, Windows Phone 8 app development, SAP Smartforms and ABAP Programming, Windows 7, Visual Studio and MS Office software Kodyaz Development Resources
Development resources, articles, tutorials, samples, codes and tools for .Net, SQL Server, Windows, Windows Phone, SAP and ABAP, like SAP UI5, Screen Personas, etc.






PERT Estimation (Program Evaluation and Review Technique)

PERT or Program Evaluation and Review Technique is used for time (activity duration) and cost estimation. PERT calculation is a special form of three-point estimation which uses optimistic, most likely and pessimistic values for cost and duration estimation. Besides giving the expected value as the result of weighted calculation, pessimistic and optimistic values enables the project managers to calculate the standard deviation and variance.

What is PERT according to PMI?
PMI defines Program Evaluation and Review Technique aka PERT as a technique for estimating that applies a weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates within PMBOK 5th Edition page 553.

PERT Program Evaluation and Review Technique

PERT (Program Evaluation and Review Technique) is a special form of Three-Point Estimating technique which is used as a tool or technique applied at Estimate Activity Durations process in Schedule Management Knowledge Area.

For more about Three-Point Estimating, PMP certification candidates can refer to PMBOK 5th Edition page 170 (6.5.2.4 Three-Point Estimating).

As PERT is a weighted average of three estimates namely as optimistic, most likely and pessimistic the formula which weights these three different estimates can be described as follows:

tE = (tO + 4*tM + tP) / 6

tE Expected: tE is the Expected value as a result of PERT Program Evaluation and Review Technique
tM Most likely: tM is the most likely estimate which is the estimate that is expected to happen for an activity duration.
tO Optimistic: tO is the minimum estimated activity duration as a result of the best-case scenario for an activity.
tP Pessimistic: tP is the pessimistic estimate or the highest value estimated for an activity duration on the worst-case scenario.

Standard deviation can be calculated as follows:

standard deviation = (tP - tO) / 6

And the variance is calculated using the below PERT formula:

variance = [ (tP - tO) / 6 ]^2


As a project manager, if you are making an estimation for a number of activities note that the standard deviation can not be summed. For example, if you have two activities namely activity A and activity B, the overall standard deviation equals to:

Standard Deviation(of A and B) = SquareRoot of [ Variance(of A) + Variance(of B) ]







Microsoft Office

Download Office 2010
Project 2010 Download

Office 2013 Download
Install Office 2013
Activate Office 2013
Project 2013 Download
Visio 2013 Download




PMP Certification and Project Management KnowHow
Risk Response Types for Project Managers in PMP Exam
Common Causes of Conflicts in Project Management
Project Management Plan Includes Sub-Plans and Baselines
PMP Exam Tips: Activity Dependency Types
Free PMP Exam Questions based on PMBOK 5th Edition
PERT Estimation (Program Evaluation and Review Technique) for Project Management
Code of Ethics and Professional Conduct
Group Decision Making Techniques for Project Managers
What are 6 Project Constraints in PMP Exam?
Project Management Conflict Resolving Techniques
Project Management PMP Certification Exam Tips
Project Management Knowledge Areas by PMI
Ishikawa Diagram (Cause and Effect, Fish-bone diagram)

Microsoft Project Download and Tutorials
Free Microsoft Project 2013 Download
Microsoft Project 2013
How to Create Master Project, SubProject in Microsoft Project 2010
Microsoft Project 2010 Download Free Trial
Microsoft Project 2010 Team Planner
Add Column to Gantt Chart in Microsoft Project 2010
Copy and Email Timeline in Microsoft Project 2010
Microsoft Project 2010 Activation Error



Copyright © 2004 - 2017 Eralper YILMAZ. All rights reserved.
Community Server by Telligent Systems