SQL Server administration and T-SQL development, Web Programming with ASP.NET, HTML5 and Javascript, Windows Phone 8 app development, SAP Smartforms and ABAP Programming, Windows 7, Visual Studio and MS Office software Kodyaz Development Resources
Development resources, articles, tutorials, samples, codes and tools for .Net, SQL Server, Windows, Windows Phone, SAP and ABAP, like SAP UI5, Screen Personas, etc.






PMP Exam Tips: Activity Dependency Types

Dependencies like discretionary (soft logic) or mandatory are used to determine the order of activities in Sequence Activities project management process. Important especially for PMP exam candidates. Activity dependencies are documented as an attribute of related activities which can be considered as project documents update.

In this PMP certification exam preparation article, I would like to share following PMP exam tips with project managers.

Activity dependency types defined for PMP exam in project management:
1. Mandatory Dependency
2. Discretionary Dependency
3. Internal Dependency
4. External Dependency

An activity can have two of the above activity dependency attributes at a time. But can not be mandatory and discretionary at the same time. Similarly an activity dependency can be either internal or external.

To summarize, an activity can have one of the following dependencies: mandatory-external, mandatory-internal, discretionary-external or discretionary-internal.


Discretionary Dependency

An important PMP exam tip for discretionary dependency is that discretionary dependencies are also referred as soft logic, preferred logic or preferential logic. Discretionary dependencies are "should be" requirements. There is a best practise behind discretionary dependency of an activity. If in the PMP exam question, there is a mention to lessons learned, business knowledge or best practises then it is probably about a discretionary dependency.


Mandatory Dependency

On the other hand, mandatory dependency is sometimes referred as hard logic in PMP exam questions. Mandatory dependencies are used for activities that are "must be", requirements from physical limitations, contracts or laws (contractually or legally mandatory requirements).


Internal Dependency

If there is not any involvement of a third party related with activities and dependencies, these are referred as internal dependencies.


External Dependency

If the activity depends on third party involvement where there is not a control of project members then this is an external dependency.







Microsoft Office

Download Office 2010
Project 2010 Download

Office 2013 Download
Install Office 2013
Activate Office 2013
Project 2013 Download
Visio 2013 Download




PMP Certification and Project Management KnowHow
Risk Response Types for Project Managers in PMP Exam
Common Causes of Conflicts in Project Management
Project Management Plan Includes Sub-Plans and Baselines
PMP Exam Tips: Activity Dependency Types
Free PMP Exam Questions based on PMBOK 5th Edition
PERT Estimation (Program Evaluation and Review Technique) for Project Management
Code of Ethics and Professional Conduct
Group Decision Making Techniques for Project Managers
What are 6 Project Constraints in PMP Exam?
Project Management Conflict Resolving Techniques
Project Management PMP Certification Exam Tips
Project Management Knowledge Areas by PMI
Ishikawa Diagram (Cause and Effect, Fish-bone diagram)

Microsoft Project Download and Tutorials
Free Microsoft Project 2013 Download
Microsoft Project 2013
How to Create Master Project, SubProject in Microsoft Project 2010
Microsoft Project 2010 Download Free Trial
Microsoft Project 2010 Team Planner
Add Column to Gantt Chart in Microsoft Project 2010
Copy and Email Timeline in Microsoft Project 2010
Microsoft Project 2010 Activation Error



Copyright © 2004 - 2017 Eralper YILMAZ. All rights reserved.
Community Server by Telligent Systems